Project Title:

Las Virgenes Road Scenic Corridor Widening Project


Las Virgenes Road between Agoura Road & Lost Hills Road

Construction Start Date:

July 2015


10 - 12 months



Project Reviews and Approvals:

Las Virgenes Road Gateway Master Plan adopted by City Council - December 2, 1998

City Council Approval of the MOU with Metro for Measure R funding - May 26, 2010

Public Workshop at the Traffic & Transportation Commission meeting - August 23, 2011

Transportation Commission meeting: Las Virgenes Scenic Corridor Widening Project Update - October 25, 2011

Transportation Commission meeting: Las Virgenes Scenic Corridor Widening Project Progress - January 24, 2012

Transportation Commission meeting: Presentation on the results of the Las Virgenes Road Scenic Corridor Widening Workshop - January 28, 2014

Public Workshop at De Anza - February 25, 2014

City Council Meeting: Construction Contact awarded to Excel Paving Company - May 27, 2015

Developer Contact:

Contact Blue Marble Development, LLC ( with questions about the Paxton Place development at 4240 las Virgenes Road


Tatiana Holden -

NEW Monday, July 11, 2016, Traffic Control on Las Virgenes Road will be changing.
Traffic Control Plan - Las Virgenes Road
The changes are as follows:

  • All traffic (north and south bound) will temporarily be moved to the west side of the road between La Paz and Willow Glen

  • Traffic control will remain the same from Willow Glen to A.E. Wright School

  • From A.E. Wright School to Lost Hills Rd, traffic will be moved to the outside lanes

Your cooperation to follow all temporary traffic control signs, marking and construction zone speed limits is appreciated.

Project Description:

The Las Virgenes Roadway Widening and Improvement project addresses the design modifications needed to provide two travel lanes in each direction, bike lanes, landscaped medians and continuous sidewalks along the eastern side of the road.

Public Outreach:


  • Letters were mailed to key property owners and/or homeowner association contacts in April of 2011.

Public Workshop:

Project Updates:

  • A pre-construction meeting is scheduled for June 18, 2015

  • Project updates were conducted at the 10/25/11, 1/24/12 and 10/23/12 TTC meetings and 9/10/14 City Council meeting.