GENERAL
PROJECT INFORMATION |
|
Project Title: |
Clover Trail Water Main Extension |
|
Location: |
Clover Trail, near intersection of Orchid
Trail, Calabasas Highlands |
|
Construction
Start Date: |
November 28, 2011 |
|
Duration: |
Three to four weeks |
|
Contact: |
Matt Baumgardner,
mbaumgardner@cityofcalabasas.com |
The water main that terminates approximately 200 feet to the east of
the intersection of Clover Trail and Orchid Trail in the Calabasas
Highlands will be extended to the frontage of the property located
at 23651 Clover Trail. The total length of the water main extension
will be approximately 360 feet. In addition to the main extension, a
new fire hydrant will be installed at the intersection of Clover
Trail and Orchid Trail (northwest corner). Laterals and new water
meters will be installed for residences located along the new water
main section.
The anticipated completion of construction is December 21st.
|
 |