2014 ANNUAL STREET RESURFACING PROJECT

GENERAL PROJECT INFORMATION

Project Title:

2014 Annual Street Resurfacing Project

Location:

Calabasas Hills Road; south entrance to Grape Arbor Park

Approvals:

City Council on August 13, 2014

Construction Start Date:

September 15, 2014

Duration:

20 working days

Contact:

Tatiana Holden, tholden@cityofcalabasas.com

October 2014  NEW

An unforeseen field condition forced the Contractor to modify the projectís schedule. Wet soil was discovered in the area scheduled for base repair. The Contractor is anticipating to continue work in this area on Friday, October 3rd.

September 2014

Rubberized asphalt overlay and base repairs of Calabasas Hills Road; asphalt removal and replacement at the south entrance to Grape Arbor Park.