2010 ANNUAL CITYWIDE RESURFACING PROJECT

    

GENERAL PROJECT INFORMATION
Project Title:

2010 Annual Citywide Resurfacing Project

Location:

A. Mulholland Highway Northern City limit to Paul Revere Rd.;
B. Parkway Calabasas Park Entrada to Camino Portal;
C. Dry Canyon Cold Creek Road - Mulholland Hwy to 700 feet east of Mulholland Hwy.

Construction Start Date:

July 26, 2010

Contract Award: May 26, 2010
Duration:

Through December 17, 2010

Contractor: Granite Construction Company
Contract Amount: $718,966.00
Contact: Tatiana Holden, tholden@cityofcalabasas.com

Construction activities for the 2010 Calabasas Annual Resurfacing Project began in July. Construction is expected to continue through October 21, 2010. There will be limited access on days when actual paving occurs, but only for a short period of time. The Contractor will re-open the streets as soon as it is safe and possible to do so. The streets will be paved one travel lane at a time, therefore, access will be provided when needed.  

This project involves the use of Asphalt Rubberized Hot Mix (ARHM) to improve certain characteristics of roads in Calabasas.  ARHM elongates the lifespan of roads and provides a suitable surface for cars to drive on.  Also, overlaying is an environmentally safe choice because it prevents pollution from the construction of repaving as well as preventing the creation of waste products that come out of ripping the pavement out of the ground.

A section of Parkway Calabasas between Camino Portal and Paseo Primario (West) has been added to the 2010 Annual Citywide Resurfacing Project. It is in need of pavement repair. About 200 linear feet suffer from pavement distress comprised in pavement cracking, erosion of the pavement surface and general deformation. This work will be completed in December.