Flow Chart C:
Permit Issuance to Final/Certificate of Occupancy |
|
Determine need for Pre Construction meeting
and schedule with project planner |
|
|
|
|
Grading Permit Application |
1. Grading Permit fees collected
2. Developer grades property
3. Rough Grading Certification submitted by developer
4. Public Works sign off of Rough Grading for Building |
|
|
|
Development Impact and Mitigation Impact
fees paid |
|
|
|
|
Building Permit and Related Permits Issued |
Types of permits typically issued include:
a) Building Permit/MEP Permits
b) Encroachment Permit
c) Oak Tree Permit |
|
|
|
Construction begins with inspections performed
at required intervals (builder responsible for requesting inspections at appropriate times,
see appropriate agency if unsure of required inspections) - Typical lead time for inspection is 24 hrs. |
Agencies that regularly inspect projects include, but is
not limited to, Public Works/Engineering, Planning,
Building and Safety, Fire Department, Los Angeles County, Las
Virgenes Municipal Water District |
|
|
|
Result of inspections may include
approval, correction notice, stop work notice, or
revisions required |
Mitigation monitoring required throughout
life of project and may include post-construction
monitoring |
|
|
|
Applicant corrects required items and
meets Punch List Items for all departments and Condition Compliance Review |
Revisions submittal may be required for completion |
|
|
|
Each required agency signs off on project when
work satisfactorily completed |
|
|
|
|
Certificate of Occupancy Issued |
|