Flow Chart B:
Post Approval Permit Process (Plan Check) |
|
Applicant discusses approved project
with case planner and proceeds as
needed |
Include process of Condition Compliance and Mitigation Measures |
|
|
Submittal for plan check
Documents submitted to the appropriate department for plan
review and correction review. Departments that review include Public
Works/Engineering, Planning and Building Services, and Transportation.
(See below for department leads and responsibilities in review
process). |
Plan check fees are due at this
time
This includes submitting and obtaining documentation of approval from
outside agencies listed in Referral Letter. |
|
|
|
Referral Letter and/or plan check
comments returned to applicant by each department |
|
|
|
|
Applicant revises plans and
resubmits to appropriate department |
IF CORRECTIONS |
|
|
Submitted plans reviewed.
Applicant notified. |
IF APPROVED
Depending on complexity and size of project,
additional DRC review may be required for condition compliance and
mitigation measure compliance. |
|
|
Final review completed and ready for permit issuance for particular stage of construction.
GO TO FLOW CHART C |
|